Monday, February 09, 2009
More construction happening on Alabama soon




We did some further investigation and found that the hole drilling actually goes from the 100 block of Bernal Heights Blvd (near Bradford), heads north/downhill to Esmerelda towards Alabama, and all the way down Alabama to Precita, where they turn East and go down Precita to Bryant.
All along this way, there are also underground survey markings for all the underground water, gas and electrical services.
It is very similar to the path that the Bernal Hills Water Pipeline takes under Bernal Hill. This is the same pipeline that was replaced over the last 18 months, and terminated at Alabama and Ripley.
Alabama street is already a major "right of way" for other utilities. There are several fiber optic lines going down Alabama (ATT, Qwest, MFN, Level 3 and CCSF/City of San Francisco's fiber ring are all ones that have manhole covers up and down the street with their names on them). We're trying to track down more details on who what the project is, and how long it will be tearing up Alabama.

Labels: bernal hills pipeline, construction, precita, water main
Sunday, January 18, 2009
Harrison Water Leaks
This is the second leak of that kind in the last year that we know of, the last one was up the hill a bit more.
The SF Water Department staff told Precita.org that the water line the 3200 block of Harrison is almost 100 years old. One house on Harrison still has the original building permit to connect to the water main dated 1910.
The water main will need to be replaced at some point in the future, else residents will be getting a lot more visits from DPW to repair the leaks the spring up. The water line is a 3" pipe going up the street. It's amazing that it has lasted as long as it has!
In the mean time, if you see any more instances of water seeping up from the street, please call 311 and report it.
Labels: construction, water main
Thursday, March 13, 2008
Water Main repair on Harrison
Mary Ann from Bernal Hill Realty sent us some pictures of the work:
Labels: construction, water main
Tuesday, August 21, 2007
The tunnel under Bernal
Construction Update: Affholder Construction, the tunneling contractor continues boring work within City property through Bernal Hill. The closure of Powhattan Street between Nevada & Nebraska (the "tunnel head") continues until October. Work continues at Cortland Avenue and Nebraska Streets. Some parking has been temporarily removed at Alabama & Ripley and traffic patterns have slightly changed. The storing of some materials and equipment is located at Powhattan & Nebraska and also at Bernal Heights Boulevard near Bradford Street.
The target completion date for this project is October 2007.
Work has now started at Ripley and Alabama, another "tunnel head". Apparently, the tunnel goes directly under some homes. The old tunnel went directly under some homes, but the new tunnel is trying to avoid going under homes. (This is what I've been told, but don't have a reference to back it up.)
Here's a map of the San Francisco water system. You can see this main on the upper left side of SF.
Labels: bernal hills pipeline, construction, water main
More in the Archives
- October 2006
- November 2006
- December 2006
- January 2007
- February 2007
- March 2007
- April 2007
- May 2007
- June 2007
- July 2007
- August 2007
- September 2007
- November 2007
- December 2007
- January 2008
- February 2008
- March 2008
- April 2008
- May 2008
- June 2008
- July 2008
- August 2008
- September 2008
- November 2008
- December 2008
- January 2009
- February 2009
- March 2009
- April 2009
- May 2009
- June 2009
- August 2009
- September 2009
- October 2009
- November 2009
- December 2009
- January 2010
- February 2010
- March 2010
- April 2010