Bernal Heights Water Pipeline update

Bernal Heights Pipeline - (Putnam, Nebraska, Powhattan, Alabama, Ripley Streets) Construction Update from
SFWATER.ORG:
Crews are currently are pressure testing the pipeline at Putnam, Nebraska and Powhattan. Upon passing all pressure tests crews will begin restoring the roadway. Crew are awaiting the arrival of the last pipe segment to complete the work at Alabama & Ripley. Some parking has been temporarily removed at Alabama & Ripley and traffic patterns have slightly changed. The storing of some materials and equipment is located at Powhattan & Nebraska and also at Bernal Heights Boulevard near Bradford Street.
Work Hours : Monday through Friday from 8:00 a.m. to 5:00 p.m.
The target completion date for this project is August 2008.
Construction on Nebraska street above Cortland:

Pipes waiting for installation on Ripley at Alabama: